| labor |   | $
|
|---|
| 1 hardware engineer (@40/hr x 440hrs) | | 17600
|
| 2 software developers (@40/hr x 440hrs) | | 35200
|
| 2 exihibit installers (@15/hr x 8hrs ) | | 240
|
| statistical researcher (@20/hr x 40hrs) | | 480
|
| subtotal | | 53520
|
| equipment/materials
|
|---|
| micro-camera | | 150
|
| md-6 critical data view | | 3600
|
| lenses |   | 300
|
| wireless setup |   | 500
|
| pc |   | 2000
|
| misc hardware |   | 400
|
| 2 couches |   | 800
|
| low table with refreshments |   | 400
|
| 3 soft spot lights |   | 180
|
| 2 floor to ceiling mirrors |   | 150
|
| subtotal | | 8480
|
| Total |   | 62000
|
|---|
|  
|
|---|
|  
|
|---|
timeline
|
| task |   | time estimate
|
|---|
| statistical research |   | 1 week
|
| hardware development |   | 8 weeks
|
| software development |   | 8 weeks
|
| system integration |   | 1 week
|
| system testing |   | 1 week
|